Agricultural Buildings and the 28 Day Rule: What Farmers Need to Know
October 2026
By Gemma Bluck, Apprentice Rural Surveyor
Many agricultural developments can be carried out under permitted development (PD) rights, potentially avoiding the need for a full application. However, understanding the requirements of Part 6 of the Town and Country Planning (General Permitted Development) (England) Order 2015 (GPDO) is essential before any project begins.
What is GDPO Part 6?
Part 6 Class A of the GDPO permits certain agricultural developments on qualifying agricultural units of 5 ha or more. These rights can allow the erection, extension, or alteration of agricultural buildings, as well as some engineering operations and private roads, where they are reasonably necessary for the purposes of agriculture. For agricultural units of less than 5 ha, development will generally fall under Class B.
Does Permitted Development Mean No Planning Permission?
Not necessarily. Many proposals still require a Prior Approval application to the Local Planning Authority (LPA) before work can begin. This process informs the council that your proposal meets the relevant criteria, including:
- Size of the Holding
Under Class A, the entire agricultural unit must be at least 5 ha and development cannot take place on a separate parcel of land smaller than 1 ha.
- Size of the Building
New and extended agricultural buildings have a maximum floor area of 1,500 sqm, reduced to 1,000 sqm for housing livestock or slurry/manure storage. The maximum height is 12 metres, or 3 metres within 3 kilometres of an aerodrome.
- Proximity to Roads and Dwellings
Development must be more than 25 metres from the metalled part of a trunk or classified road. Where the proposed building is within 400 metres of a protected dwelling, it cannot be used for housing livestock or storing slurry.
- Agricultural Need
The development must be genuinely required for agricultural purposes and be reasonably necessary for the purposes of agriculture.
- Two Year Rule
The cumulative footprint of any new building space, excavations or private ways added across the agricultural unit within any rolling two year period cannot exceed the permitted thresholds. The calculation must also take into account development carried out within 90 metres of the proposed site during the preceding two years.
What Is The 28 Day Rule?
Once the LPA receives a valid Prior Approval application, it has 28 days to determine whether prior approval is not required, is required for further assessment, or should be refused. If no decision is issued within 28 days, development can usually proceed.